Bethel Building Project Timeline
– 2008 –
– 2008 –
- Bethel Presbyterian Church Groundbreaking December 30, 2007
- Vacate and remove salvageable items by January 4 DONE
- Vacate Worship Space and tow story Sunday School rooms January 4 DONE
- Meet with Historical Society DONE
- Vacate Church Offices by January 11 DONE
- Begin Joint Worship with KUM DONE
- Meeting with Zoning/Variance Board (January 8th 5:30 Community Center)
- Commence Site Excavation January 11
- Remove Organ DONE
- Remove Pews
- Vacate Worship Space and two story Sunday School rooms January 4
- Begin the 10 Month Construction Schedule